
Main grid service fees remain unchanged
Main grid service fees will remain unchanged in 2021.

Main grid service fees will remain unchanged in 2021.

Constructing a transmission line is a long process, which first sees the light of day on a map, many years before becoming a feature of the landscape. Nowadays, future transmission line rights-of-way can be presented to landowners and partners with the help of 3D modelling.

Expropriation is a normal means of executing a linear construction project. The procedure begins when the project commences and an expropriation permit application is submitted, and it ends when compensation is assessed and paid following construction work. Landowners have the opportunity to give their views on the transmission line route during the planning phase and the expropriation permit application phase.

Control Centre Manager Maarit Uusitalo is responsible for managing the power balance on the main grid and the power system from the office in Käpylä. Uusitalo, who has worked for Fingrid for a long period in several positions, took on the role of control centre manager in March this year.

Fingrid’s transmission line brochures for landowners have been updated. There were previously four brochures: two about the construction phase and two for the period after construction. As a result of the update, there are now two brochures.

New wind turbines and a pumped storage facility are planned in the municipality of Haapajärvi and its surrounding areas.

The design of the main grid includes making preparations for a climate-neutral society in which the importance of electricity is constantly increasing. Over the coming decades, the emissions produced by generating electricity must be lowered, and electricity consumers must be offered the best opportunities to obtain clean electricity.

Fingrid aims to be well prepared for the future. Its research and development projects range from data screening to flexible market pilot projects and bottleneck management.

Fingrid is currently building transmission lines on the main grid on dozens of sites. Construction work on the main grid runs to EUR 100 million annually. The company is having a record year in terms of the number of substation modernisations and refurbishments.

The Imatra hydroelectric power plant began operating in 1929, along with the Imatra substation, which was the first substation on Finland’s main grid. The first transmission line on the main grid went from Imatra to Vyborg and onwards to Helsinki and Turku via Hikiä. In 2020, Fingrid commissioned a new substation in Imatra and began modernising the Imatra–Huutokoski transmission line.