Search
Close this search box.

Work cannot proceed without a crossing statement 

Share
Heidi Oja and Max Isaksson write crossing statements for Fingrid. In recent times, 400–500 statements have been written each year, and the rate is only increasing. But what is a crossing statement?

Heidi Oja and Max Isaksson say that a crossing arises when a landowner wants to do work such as dig a ditch or clear a field beneath a transmission line.

“Crossings also occur when roads or car parks are built or from overhead lines and lighting if there are transmission lines in the area. Crossings are all activities or events that occur near transmission lines,” they say.

A crossing statement is required in order for a project planned in the area to be executed safely.

“This also helps to ensure that electricity transmission is not disrupted. The statement does not explicitly approve or reject any plans. Instead, it sets appropriate limits for the construction or event,” Max Isaksson summarises.

Statement requests can be sent by email, letter or on Fingrid’s map service – and people are always welcome to call, the pair say.

High completion rate

Crossing statements are always issued in writing. They come with a map showing the transmission lines and the construction site. Crossing statements provide guidelines on where and how the site can be safely built on. At present, almost all crossing sites can be implemented, as long as the plan is fine-tuned to ensure the correct safety distances.

Why are more and more statements needed? – Oja and Isaksson list a few reasons: firstly, the number of transmission lines has increased.

“The plans call for many more transmission lines to be built in the future,” Heidi Oja states.

And the more the grid is strengthened, the greater the earth fault current and earthing voltages will be. This increases the importance of coordinating crossings and transmission lines.

Underground cables coming soon

Heidi Oja and Max Isaksson state that operators in the sector seeking to reduce the amount of storm damage to their networks are rapidly switching from overhead lines to underground cables, including near Fingrid’s lines.

“Nowadays, all overhead lines that cross transmission lines are being replaced by underground cables, also to facilitate the construction of our transmission lines,” Heidi Oja says.

The rate of activity in the field is further increased by the fact that a large number of cable links are built near new connection stations due to factors such as the increase in wind power generation.

According to the duo, crossing statements should be requested well in advance of the start of construction, and the statements are usually delivered on time. However, approximately once per month, a situation arises where someone sitting in a work machine phones and asks if they can start digging.

“In urgent situations like these, we strive to respond very quickly, and we have been quite successful in doing this,” Oja and Isaksson state.

In simple cases, a statement can be completed in one day, but if information needs to be collected from various parties before a statement can be prepared, the process could take several weeks.

Wide-ranging teamwork

Heidi Oja and Max Isaksson have been preparing statements since 2007, so they have the necessary expertise to respond to extensive and complex requests. However, they do not run the whole show alone: they are currently assisted by a fixed-term planner and two part-time trainees.

“We have long had students from higher education institutions working with us, and they have been responsible for work such as mapping,” Heidi Oja says.

Fingrid’s regional organisations also provide solid support.

“Ultimately, the transmission line experts in various regions are the ones who contact customers the most,” Oja says.

“Fault current counters, line route planners and line project managers are important partners for us.”

 

 

Streamlining the torrent of statements

’Streamlining the crossing statement process’ took first place in Fingrid’s internal contest among development projects – known as the Virta projects – in 2020.

Fingrid’s crossing statement function created an impact analysis tool to identify which project should be initiated first. The Virta steering group’s evaluation specifically acknowledged the help that the model provided to other parties.

Max Isaksson from the crossing statement function says that the streamlining process mainly focused on eliminating bottlenecks.

“One of these was the large amount of paper moving around the company. In this regard, we made a leap into the digital realm in order to get rid of the unnecessary paperwork,” he says.

Another example was the effort to locate and reduce the amount of overlapping work.

“Cases like this arose when entries were made in different systems or archiving. We succeeded in cutting out a lot of unnecessary things.”

According to Max Isaksson, this thorough review of the function’s operating methods was an interesting and educational experience that will continue to bear fruit long into the future.

“We were able to deploy some of the improvements we developed immediately, while the implementation of the rest will still need to be planned.”

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *